DevelopmentTuesday, November 3
Brambleton neighbors get an open house Thursday on STACK's data centers and substation
The Leesburg Today team
The Brambleton Community Association and STACK Infrastructure are hosting an open house on the planned data center and proposed substation near Evergreen Mills and Belmont Ridge roads from 7 to 8:30 p.m. Thu., Nov. 5 at the Barn in Brambleton, 24439 Evergreen Mills Rd.
STACK's Shreveport South project by the numbers
- 95 acres
- fronting Evergreen Mills Road
- 114
- diesel generators planned for backup power
- 265 feet
- from the nearest home
Source: loudounnow.com
Residents have been vocal. At an Oct. 27 town hall, Supervisor Laura A. TeKrony and County Chair Phyllis Randall pointed to a separate application, a Northern Virginia Electric Cooperative substation meant to power the data centers. Supervisors said opposing it may be a way to stop their development.
“My daughters are eight and six years old. My youngest has asthma. We are totally opposed to this.”
- Project: two three-story buildings, up to 60 feet tall
- Zoning: 1993 rules apply because the application dates to 2023
- Approved: May 2025
The proposed data centers would total 1.3 million square feet
Floor area of the proposed data centers, beside places you know
23 football fields would fit inside the proposed data centers
Source: loudounnow.com
View as table
| Floor area | |
|---|---|
| The proposed data centers | 1,300,000 sq. ft. (Two buildings) |
| A football field | 57,600 sq. ft. (end zones included) |
| A Walmart Supercenter | about 180,000 sq. ft. |
Sources: Loudoun Times-Mirror, loudounnow.com