Loudoun supervisors approve the Golden substation after Dominion agrees to power a data center sooner

The Leesburg Today teamFrom the Nov. 7 edition · 1 min read · 2 sources

ShareEmailFacebookX

If you've followed Loudoun's power line fight, there's movement. The Board of Supervisors approved Dominion Energy's Golden substation application Thursday, after Dominion agreed to bring power to a Sterling data center 12 years ahead of schedule.

runs its Glenn Drive data center on gas turbines around the clock, after learning Dominion couldn't provide power until 2040. Under the new agreement, Dominion would provide power in two years. Residents have raised concerns about constant high-pitched noise and emissions from the turbines.

Dominion agreed to power the Sterling data center 12 years early

2040
when Dominion said it could power Vantage's data center
2 years
until Dominion would provide power under the new agreement
12 years
ahead of schedule for the data center's power
  • Vote: Thu., Nov. 5, after months of delay
  • Board's reach: it decides on substations, not power lines
  • Golden to Mars lines: approved them overhead

Residents around Loudoun Valley Estates, where the line is expected to run in backyards and on HOA open space, have opposed it, and the county government and School Board have pushed to bury it. The board's other Nov. 5 votes covered pay raises, labor agreements, LCPS funding and legislative priorities.

The Golden substation vote moved from December to Nov. 5

  1. SeptemberSaines delayed the vote until December.
  2. OctoberSaines cited a Dominion-Vantage agreement and moved the vote up to Nov. 5.
  3. Nov. 5Supervisors approved Dominion's Golden substation application.

Sources: loudounnow.com, Loudoun Times-Mirror