Loudoun County pauses new data center applications while it rewrites siting rules
The Leesburg Today team
If you live near a planned data center, this one's for you. The Board of Supervisors voted Tuesday night to pause processing new applications while the county updates its siting standards. Reports differ on the details: one has a 7-1-1 vote and a one-year pause, another a 7-1 vote and 10 months.
The county counts about 245 data center facilities built or under construction, totaling 58 million square feet, with another 55 million approved or under review. Board member Juli Briskman, who led the push, said staff estimate the pause could affect 33 active applications for data centers and substations. Data centers brought in more than $1 billion in tax revenue this year, and the Data Center Coalition's Nicole Riley testified that a moratorium could invite legal challenges.
Loudoun has 58 million square feet of data centers built or under construction
Source: Royal Examiner
View as table
| Value | |
|---|---|
| Built or under construction (sq. ft.) | 58M |
| Approved or under review (sq. ft.) | 55M |
- Phase two: siting near schools and homes, height limits, noise, onsite power
- Exempt: projects grandfathered into by-right permitting
- Existing applications: can still move forward on a case-by-case review
- Phase two expected done: July 2027
Loudoun's data center rewrite reaches phase two and runs to July 2027
- MarchThe county completed phase one and the board eliminated by-right data center development.
- Nov. 17The Board of Supervisors voted to pause new data center applications.
- July 2027The county expects to complete phase two of the siting and zoning rewrite.
Sources: Royal Examiner, FOX 5 DC