Board of SupervisorsTop story
Loudoun supervisors approve a 12-month pause on data center and substation applications
Seven of nine supervisors voted for the pause
7 of 9
- voted for the pause
- 2 voted no or abstained
Source: Virginia Business
View as table
| Count | Share | |
|---|---|---|
| voted for the pause | 7 | 78% |
| voted no or abstained | 2 | 22% |
Loudoun supervisors voted 7-1, with one abstention, Tuesday to pause data center and substation applications. The Board of Supervisors will hold off until it finishes updates to its zoning ordinance and comprehensive plan. The pause is retroactive to Sept. 15.
Why 12 months? County Attorney Leo Rogers said the board can't impose a moratorium on a particular use. State code does set 12-month deadlines for reviewing legislative applications, and a pause can fit inside that window.
“I am very worried about the amount of litigation that is about to head our way.”
Supervisor Kristen Umstattd, the lone no vote
- Exempt: applications in specialized tax districts, like the Rt. 28 Tax District
- Exempt: substations deemed necessary for "grid reliability"
- Staff keeps accepting applications; they wait in a backlog
- After the pause: five proposals per meeting, at most
The pause took four months to move from proposal to vote
- JulySupervisors Juli E. Briskman and Laura A. TeKrony start the push for a data center pause.
- Sept. 15Retroactive start of the pause on data center and substation applications.
- Nov. 17Supervisors vote 7-1, with one abstention, to approve the 12-month pause.
- July 2027Phase Two of the data center standards could be finished, per Briskman.
Sources: LoudounNow.com, Virginia Business
Public comment ran more than 90 minutes, with speakers on both sides. Supporters cited noise, emissions, environmental impacts and the need for new transmission lines, including the planned Valley Link line near Lovettsville.